Decided 5 October: one data layer that Aleph owns.
Fiona and Annette are running it.
Decided 5 October: TopNotch builds it.
DoneNowWaiting on a decisionTo come
The same 8 inputs sit in all 3 levels. A gives each its own slide. B folds them into 5 questions. C shows only what moved.
Fairmas is unchanged throughout. In parallel, Rudolf is asked whether BIRD could sit on Aleph’s own storage; both options come back to the 3 of you.
Fairmas, Medallia, CoStar. Already clean and the same for every hotel.
Of each review pre-built from the layer. Neil’s bar for version 1.
To build one pack by hand, every month. One cluster’s own figure.
Our first shape, from the engineer’s start to the first half-built review. The engineer confirms it after discovery.
Fairmas stays at every hotel it serves. Nothing spent on it is lost.
Scope of work (Excel): written after meeting HR on 1 October, checked against their answers, and shared with both suppliers as a first version.
Its own platform. Proposal of 20 September; GO-Globe says it covers the scope of work.
A custom build. Proposal of 2 October, against the scope of work.
Decided 5 October: TopNotch. Neil negotiates the price directly. Both suppliers had the same scope; TopNotch priced it line by line. GO-Globe’s proposal stays here for the record.
The account manager’s name, from Rohit. The engineer’s first conversation.
Requirements from us by 7 October, Bani reviews, Aleph hires. Bani has a candidate to introduce.
Can BIRD sit on Aleph’s own storage, and what is the price for a 70-room hotel. Asked this week.
1 July to 30 November. Work under way, a dot for each thing delivered · Waiting on a decision · Planned, or starts when you say so
Raised, not started: A a project tool for Fiona · B one tiered procedure library for the portfolio · C owner onboarding, signature to opening. Your call.
Agreement: 5 months, July to November; this is month 4. Invoices: July settled 16 September; August issued 26 August, due 25 September, open.